Perfect Trail System Project - April 24, 2024 Update
The wayfinding signs at Jenkins Park are nearly complete.
The wayfinding signs at Jenkins Park are nearly complete.
911 Location marker signs are being installed at along the trails at Jenkins Park and Hollaway Park.
A new Texas state symbols sign has been installed at Jenkins Park.
A new wayfinding sign for Jenkins Park is being installed near the playground.
A new wayfinding sign is being prepared at the Baytown Bark Park at Jenkins Park.
What-3-Words 911 location signs are being prepared for installation. These code words can help first responders find a caller's exact location during an emergency.
The bridges at Jenkins Park have received fresh paint.
Park teams are cleaning rust from the Jenkins Park bridges and will soon be repainting.
A Teqball table has been installed near the Jenkins Soccer Field.
The lighting at Holloway Trail has been installed and tested.
The National Fitness Court installation is complete.
Installation of the National Fitness Court has begun.
The first light pole has gone up at the Holloway trail.
Concrete has been placed for the coming National Fitness Court.
Forms have been put down so that the light installation progress can start.
Holes have been marked through the trail so that lights can be installed.
The old concrete was removed in the fitness area at Jenkins Park in preparation of a future National Fitness Court.
With the newly installed City of Baytown logo making the sign complete, the next phase of this project will be focused on 911 markers along the trails.
The new sign at Jenkins Park will set the standard for future signage for all City of Baytown parks.